ISSUE 010 · RESEARCH EXPLAINER

Why is Paraguay attracting data centers?

Energy, the grid, fiber, talent, cybersecurity and delivery risks

Paraguay’s advantage is not simply cheap electricity. Transmission, redundancy, fiber, latency, talent, security and contracts also matter for a data center. We separate national attractions from the specific conditions that still need checking at each site.

The main conclusion

Paraguay is attractive because of its combination of clean energy, expansion of the 500 kV grid, growing international connectivity and a technology-training agenda. But this does not establish that any site is already suitable for hyperscale operations: firm power capacity, electrical redundancy, physical fiber routes, latency, talent and contractual conditions remain critical variables.

LOCATION THESIS

Six factors: opportunities and risks at the same time

ENERGYAdvantageclean hydropower base
500 kVTransmissionexpansion through Yguazú–Valenzuela and other works
1,927.68 GbpsInternational connectivityCONATEL figure for fixed internet in 2024
249 municipalitiesFiberexpansion reported by CONATEL/FSU
TALENTEcosystemUPTP and Distrito Innova
REDUNDANCYRiskANDE acknowledges the need to strengthen transmission
01 · ENERGY ADVANTAGE

Clean energy is the first reason Paraguay attracts attention

Paraguay’s electricity mix relies on large hydroelectric plants such as Itaipú, Yacyretá and Acaray. MITIC and MIC have proposed turning that energy base into digital activities with greater added value, including AI, cloud services and data centers.

For an operator, cost and long-term availability matter. But national abundance does not replace the operational question: how much power can be connected at a particular site, when, from which infrastructure, with what quality, redundancy and contract?

02 · GRID CAPACITY

The transmission grid is expanding; that is precisely why it should not be treated as a settled issue

ANDE is building the approximately 200 km, double-circuit 500 kV Yguazú–Valenzuela line to strengthen transmission capacity and reliability. The Master Plan also includes strategic works such as the second 500 kV Itaipú–Villa Hayes line.

After a system event in February 2026, ANDE explained that a double contingency during high demand affected a grid that did not yet have the necessary transmission-level redundancy. This evidence requires distinguishing abundant generation from a fully redundant grid for large loads.

03 · FIBER & INTERNATIONAL CONNECTIVITY

Connectivity has improved sharply, but a data center needs site-level information

CONATEL’s Fixed Internet report shows that international connectivity rose from 195 Gbps in 2019 to 1,927.68 Gbps in 2024. CONATEL also reports that Universal Services Fund projects brought fiber optics to 249 municipalities.

These are signs of national expansion, not guarantees of multiple carriers, physically separate routes, dedicated capacity or latency to cloud hubs from a specific site. For hyperscale operations, the decisive information is the site’s network design, not the national average.

04 · TALENT & ECOSYSTEM

A second potential advantage is developing talent around computing

MITIC presents Distrito Innova as a space bringing together academia—with UPTP as one of its pillars—applied research, industry and government. Its objectives include knowledge, investment, training and job opportunities.

That direction supports a data center strategy, but sufficient public statistics to measure the current supply of AI, high-performance computing and data center operations specialists against possible large-scale demand remain difficult to obtain. Talent availability must be checked, not assumed.

05 · CYBERSECURITY & TRUST

For sovereign AI and critical workloads, security is infrastructure too

CERT-PY, part of MITIC, coordinates national incident prevention, detection and response capabilities. MITIC also lists availability, security and interoperability among the requirements for its digital infrastructure and public data centers.

However, national capabilities do not replace a facility’s security design: a security operations center, physical controls, segmentation, zero-trust architecture, continuity and compliance must be defined for each operation and customer.

06 · INVESTMENT CASE

Economic policy aims to make data centers more than a way to sell energy

In September 2026, MIC argued that attracting AI infrastructure should benefit the knowledge economy and open opportunities for local developers, entrepreneurs and investors, rather than being limited to energy consumption.

This offers a useful way to measure results: alongside installed MW, track business adoption, research, specialized jobs, transfer of skills, cloud and cybersecurity services, and new businesses around the infrastructure.

07 · RISK CHECKLIST

Seven questions investors should answer before finalizing the investment case

① Firm connection capacity at the site, ② interconnection date, ③ electrical redundancy, ④ multiple carriers and physically separate routes, ⑤ measured latency to cloud hubs, ⑥ hiring and training plans, and ⑦ long-term contracts for energy, land and operations.

Public sources indicate favorable developments in energy, transmission, connectivity and talent, but do not demonstrate that these seven conditions are already settled for every project. This gap should be treated as due diligence still to be completed.

Five layers for assessing a location

ENERGY → GRID → FIBER → TALENT / CYBERSECURITY → CONTRACTS. Competitive advantage emerges when all five layers work at the same time.

ISSUE 010 · TOPIC CLUSTER

Next: 10 MW, 100 MW, 1 GW and electricity demand

After reviewing the case for a location, separate computing capacity from electricity demand and compare the scale with ANDE’s outlook.

Read the electricity demand guide →

Read what is confirmed about Yguazú Digital →
Return to the main article in Issue 010 →